Job Scheduling with Deadlines
Problem
Given jobs as [deadline, profit] pairs where each job takes one unit of time and only one job runs per slot, return the maximum total profit from jobs finished before their deadlines.
Sort jobs by descending profit and greedily place each in the latest free slot at or before its deadline, skipping jobs whose slots are all taken. Return 0 for no jobs.
Hint
Placing a high-profit job as late as possible keeps earlier slots free for tighter deadlines.
Test cases
case 1
in: [[[2,100],[1,19],[2,27],[1,25],[3,15]]]
expected: 142
case 2
in: [[[1,5],[1,10],[1,20]]]
expected: 20
case 3
in: [[[2,10],[1,5]]]
expected: 15
case 4
in: [[[1,1]]]
expected: 1
case 5
in: [[]]
expected: 0
Starter codePython
def job_scheduling_max_profit(jobs):
# Your code here
pass5 test cases · run your code against them in the editor